Patrick Henry Schools had a high school where the systems had aged into one another. The underground storm and sanitary piping was judged too fragile to patch and had to come out from under the slab. The building was not air conditioned, there was no fire sprinkler system, and the return air path ran through louvers in the classroom doors to the corridor and up to the units — a route that no longer met code. Five of the eight roof sections were coming off, one of them a ballasted membrane dating to 1981. Fixing any one of those meant opening the floor, the ceiling or the roof that the others also needed opened, so the district bought them together, as a single design-build agreement pre-bid through TIPS contract 181101.
The building was converted to chilled-water cooling: one 180-nominal-ton air-cooled chiller with a dual-pump package feeding five tri-deck multizone rooftop units sized to the existing curbs, with the chilled water charged to 30 percent glycol for the run across the roof. New PVC storm piping in 4-inch through 12-inch sizes was tied back to 18 existing risers, with new sanitary below the slab and the restrooms rebuilt to current code. Five roof sections were rebuilt to an average R-25 under fully adhered 75-mil EPDM carrying a 30-year warranty. Inside, the district got LVT in classrooms, epoxy in the corridors, quarry tile in the kitchen, a new gym floor, roughly 1,177 seats of motorized telescopic bleachers, 464 LED flat panels with occupancy sensors and 41 dimmer zones, new ceilings, doors, lockers, casework and classroom furniture. At the stadium, six old poles came out and four new LED poles went in near the 20-yard lines, designed for an average of 50 horizontal foot-candles on the field.
Work started in March 2020, the building was ready for classes on September 1 that year under a temporary certificate of occupancy, and the corridor epoxy was finished over the winter break on January 4, 2021. Amendment No. 1, signed that same January, is part of this project: it removed the gymnasium video system and the gym and stadium sound systems, changed the gym floor to a build-up over the existing sleepers instead of a full tear-out, and redirected the difference into what demolition had exposed.
Technical Discussion
Customer Testimonial
Konnie Meyer
Board Member · Advocate · 5 years ago
Longtime Patrick Henry community member Konnie Meyer reflects on just how much the school has changed after the renovation project, calling the transformation “mind-boggling.” She talks about improvements throughout the building and campus—from the roof, windows, and landscaping to plumbing, wiring, air conditioning, classrooms, the cafeteria, and the gym—and the pride those upgrades have created for students, staff, and the community. Prodigy Building Solutions has worked with Patrick Henry Schools on facility improvements including gymnasium renovations, energy-efficient LED lighting upgrades, and a middle school restroom expansion. The result is a more modern, functional learning environment that the Patrick Henry community can be proud of, and a great example of the impact thoughtful school renovation can have for an Ohio school district.














































