•••
Rendering of the Walnut Ridge wrestling room with team wall graphics
Athletic FacilitiesCentral OhioColumbusEqualis Gordian

Walnut Ridge Wrestling and Weight Room Renovation 2026

Walnut Ridge High School's wrestling room is rebuilt and bigger, made by moving a masonry wall rather than adding to the building. Prodigy abated the asbestos flooring and pipe insulation, ran new underground plumbing, ground and polished the concrete floor, and finished the room with new wall pads and mats, LED lighting, a fire-rated entry door, a bottle-filling drinking fountain and a wall graphic. A weight room and accessible locker rooms are designed as the next phase. Columbus City Schools bought the work through its pre-bid Gordian job order contract.

Columbus City Schools wanted a bigger wrestling room at Walnut Ridge High School, a weight room the building did not have, and locker rooms that meet current accessibility standards — without adding a square foot to the footprint. The plan takes the space from inside. The masonry wall between the wrestling room and the boys' locker room comes down and is rebuilt in a new position, and the vocal room, the practice rooms and the masonry walls between them are demolished to make the new fitness floor.

Phase 1A, the wrestling room, is executed and complete. Asbestos floor tile and pipe insulation were abated, the slab was opened for new underground plumbing and patched, and the concrete floor was ground, polished and sealed rather than covered. The room has new wall pads and floor mats reconfigured around the infilled openings, relocated outlets clear of the pads, LED strip lighting with new exit signs and emergency lights, a 60-minute fire-rated entry door and frame, a bi-level drinking fountain and bottle filler on new water and sanitary lines, and a wall graphic.

Phase 1B has not been built. It is a proposal drawn against the project contingency, covering the fitness room, men's and women's locker rooms, an officials' locker room, a trainer's room and a laundry room, and its City of Columbus permit was submitted in January 2026. As proposed, it includes owner-specified Rogue equipment on rubber fitness flooring, three grade-mounted rooftop units on new pads outside the fitness wall, two ADA showers and a three-station solid surface sink in each locker room, epoxy flake flooring, a trainer's room with an ice machine and a floor drain, and a laundry room with a 60-pound washer and a 75-pound dryer. Both phases run under Columbus City Schools' Gordian job order contract, with the district's 20 percent LEDE participation requirement met on the mechanical and plumbing package.

Rendering of the Walnut Ridge fitness area with Scots branding on the wall
Rendering of the Walnut Ridge weight room with racks and cardio equipment
Rendering of the Walnut Ridge fitness area with selectorized machines
Rendering of the Walnut Ridge weight room from the entry

Technical Discussion

Where the air handlers go when there is no roof to use

Turning a wrestling room, a choir room and a set of practice rooms into an expanded wrestling room and a new fitness center meant new mechanical systems for spaces that had been served by ceiling-hung units and a packaged unit outside the vocal room. The building offered no roof to set new equipment on, so the mechanical design started from the ground.

Section at the Walnut Ridge fitness room wall: a grade-mounted air handling unit on a concrete pad outside, ducted through a new opening cut in the brick and block wall under a steel lintel, with a 4-inch gravel-filled hole drilled 3 feet into the asphalt to take the condensate.
Figure 1 — With no roof to use, the units sit on pads, the wall carries the opening, and the pavement takes the condensate.

Grade-mounted units

Three rooftop-style units were set on new concrete pads at grade outside the fitness room wall. Getting their air into the building meant cutting an opening through brick and block and setting a steel lintel to carry the wall above it. Grade mounting has a cost in wall work and a benefit in service: a technician reaches the unit from a ladder-free pad, and the building never carries the weight or the roof penetrations of new rooftop equipment.

Condensate into the ground

A cooling unit outdoors makes condensate that has to go somewhere, and there was no drain at the pads. At each unit a 4-inch hole was core-drilled 3 feet into the asphalt and filled with gravel, a small dry well that takes the condensate below the pavement instead of letting it run across it and freeze in the winter.

Two small rooms, two small systems

The office and the laundry room have loads that have nothing to do with a gym floor, so each received a ductless mini-split rather than a branch off the fitness room's unit. A laundry room with a dryer running is not a room to condition on a wrestling room's schedule.

The fire-rated wall

The west wall of the wrestling room was furred and finished with 5/8-inch gypsum board carried to the deck and around the concrete beams to make a fire-rated barrier, and the new entry received a 60-minute rated door and frame. Those are trades an addition would never have needed, and they are still the cheaper end of finding square footage inside a building the district already owns.

When you renovate inside an existing building, ask early where the new equipment will sit. If the answer is the ground, the wall opening, the pad and the condensate path belong in the first drawing, not the last change order.

Our Work

Similar Projects